Four long-span arches changed the crossings over the US 59 trench. The archive also records the June 2001 flood, when water rose nearly to the top of that trench.
↗ EnlargePhoto contributed by Don "The Emissary" Seributra.
The bridge stayed above water. The trench did not.
Explore the Museum District sequence
The trench filled with water
June 2001 flood
June 2001
2 archive photographsMassive flooding in Houston in June 2001 filled the US 59 trench, nearly to the very top.
August and June 2000
Arched bridge construction
August 2000
1 archive photographsAugust 2000
June 2000
3 archive photographsJune 2000
The elevated freeway, Montrose and orientation
The next project and location map
Next project: demolishing the elevated structure
2 archive photographs
2001 archive
Existing elevated US 59 structure

2001 archive
Existing Montrose Boulevard overpass
US 59 Museum District construction location
1 archive photographsFrom the original archive
US 59 Museum District
US 59 Museum District
| Project | Addition of 2 HOV lanes to existing 10-lane freeway. |
|---|---|
| Cost | $32.5 million |
| Begin | Q3 1999 |
This improvement project has added the distinctive long-span arched bridges over the trench. The spans are approximately 217 feet (66m) long. The project will add 2 HOV lanes, but will not add any general purpose lanes to the existing 10 lanes. This project is a prelude to the bigger and potentially hugely disruptive next phase: demolishing the adjacent elevated freeway and placing the freeway in a trench. That project could begin in 2002.
Next project: demolishing the elevated structure
Originally, TxDOT planned to add a second elevated deck for HOV to the existing elevated freeway. The local neighborhood is high-income and very "inner loop" (read liberal and anti-freeway), so they wanted nothing of the second elevated deck. The next proposal was to make the existing deck wider to accomodate the HOV lanes. This was feasible, but right-of-way was severely constrained on the north side by a historic structure and on the south side by high voltage lines. The neighborhood still wasn't happy, because they really wanted to get rid of the elevated freeway. A leading candidate under consideration at that point was to put the freeway in a cut-and-cover tunnel. Fortunately, the cost eliminated that option. The final plan places 59 in a trench. There is talk of building a "signature" bridge where Montrose will cross the trench.