Katy Freeway in August 2001: Perry Asks for a Faster Schedule
The governor wanted reconstruction funded sooner. Toll lanes remained an option, while a statewide financing proposal reached beyond the Katy project.
↗ EnlargeCollection: TexasFreeway Katy Freeway photographs
Old Katy Road, before the reconstruction · May 2001
Old Katy Road west of WilcrestMay 20, 2001Old Katy Road runs beside former railroad land between Wilcrest and Kirkwood in this May 20, 2001 photograph. The existing freeway is visible to the left. This earlier view shows part of the corridor awaiting reconstruction, rather than work financed by the August announcement.
Original image caption
K. (high resolution 137k) Looking west along former railroad corridor and Old Katy Road on the north side of IH-10 between Wilcrest and Kirkwood. The railroad right-of-way and Old Katy Road will be consumed by the future freeway. The existing freeway can be seen on the left. Photo taken 20-May-01.
TexasFreeway commentary · The quotation panel reproduces a brief attributed passage from the original reporting. Surrounding prose is new analysis of that period.
01 / August 13, 2001
West Houston’s main street needed a different schedule
Calling the Katy Freeway west Houston’s main street was a good way to describe its reach. The road served trips between Katy, the Memorial villages and the West Loop, as well as traffic passing through the region. On August 13, 2001, Governor Rick Perry asked the Texas Transportation Commission to fund its reconstruction faster. The Associated Press report carried by the Houston Chronicle held out 2009 as a possible end to the wait.
“The Katy Freeway is west Houston's main street,”
The project in this announcement was a $952 million reconstruction of twenty miles from the West Loop to Katy, with construction scheduled to begin in 2003. Perry was asking for a faster funding commitment before that work began. Commission chairman John W. Johnson attended the announcement, and the three-member commission was expected to approve the request on August 30. An expected vote still left a decision to be made.
02 / The state’s timetable
A promise to build could arrive in installments
Perry described a funding system in which money for a metropolitan highway was authorized gradually over several years. That could leave a project approved in principle while individual construction contracts waited for their turn. A faster commitment was meant to let the work proceed with fewer gaps. For drivers, that difference concerned the length of the construction period, not simply the size of the finished freeway.
The physical corridor already needed room for a larger road. In the May 20 photograph above, Old Katy Road runs beside the grassy former railroad corridor between Wilcrest and Kirkwood. I-10 traffic is visible to the left, with office buildings and car dealerships on either side. The contemporary Katy Freeway photographs show the land and roadside development a reconstruction program had to work around.
Culberson had made freeway improvements a major campaign issue and pledged to secure federal money. Perry, meanwhile, accused the Clinton administration of discriminating against Texas in discretionary transportation funding and expressed confidence in President George W. Bush. Those were the governor’s political claims. The announcement did not supply an independent accounting that demonstrated them. The immediate request was one the Texas commission itself would have to act on.
03 / Separate claims
Tolls were an option; cleaner air was an argument
Harris County Judge Bob Eckels’ toll-road proposal remained a possible funding mechanism, but the reconstruction plan described in this report did not rely on toll proceeds. That point is easy to lose when reading the year’s Katy headlines together. April’s expansion debate emphasized the possible advantages of toll lanes; the August announcement sought faster state funding for a project that officials said could proceed without that revenue.
Air quality was another part of the argument. Eckels warned that Houston’s smog problems might restrain other road projects. He and other officials presented the Katy expansion as a way to reduce pollution by keeping vehicles moving. Bunker Hill Village Mayor Bill Marshall blamed cars sitting on freeways for much of the pollution. These were claims made in support of widening, rather than measurements of what the completed road would achieve.
Marshall represented one of six small communities at the eastern end of the project that had negotiated proposed land seizures. The demand for a faster road therefore existed alongside the work of accommodating a wider one. A shorter construction schedule could appeal to motorists while leaving property and design questions to be resolved.
04 / Proposition 15
The November funding proposal reached beyond Katy
Perry used the Katy announcement to promote Proposition 15, the November ballot proposal for a bond-financed Texas Mobility Fund. Borrowing would offer another way to build roads sooner, rather than waiting for funding to accumulate under the existing system. The AP account explicitly said Katy construction should proceed with or without that expanded funding authority. The local request and the statewide ballot proposal were related, but Katy was not described as waiting on the election.
Perry also promoted Proposition 2 for roads in border colonias. His Houston appearance tied one heavily used freeway to a broader campaign for transportation financing. For Katy, the next concrete event was closer than November: the August 30 commission meeting, where the accelerated funding request would receive its vote.