HOUSTON ARCHIVE · COMMENTARY
Houston’s Road Plan and Smog Dispute in 2001
Houston’s highway plan allowed more vehicle pollution than its new smog plan. Two reports follow the threat to Katy Freeway and Grand Parkway funding, then the May settlement that kept planning moving under the stricter limit.
↗ EnlargeCollection: TexasFreeway Katy Freeway photographs
Katy Freeway’s narrow corridor · May 2001
Main lanes beside the frontage roadMay 20, 2001A narrow strip separates Katy Freeway traffic from the frontage road between Voss and Campbell on May 20, 2001. This photograph, taken after the settlement, locates a corridor whose planned widening had been exposed to the funding threat.
Original image caption
H. (high resolution 114k) Looking west along the freeway between Voss and Campbell, where the existing right-of-way is extremely narrow. There is no space between the main lanes and the feeder! Photo taken 20-May-01.
TexasFreeway commentary · Selected passages from Eric Berger’s February 18 and Bill Dawson’s May 10, 2001 Houston Chronicle reports appear in quotation panels. The surrounding narrative explains the dispute and settlement.
01 / February 18, 2001
February: two plans, two pollution limits
Houston’s road planners were preparing for a freeway expansion that their pollution budget might not allow. In Eric Berger’s February 18, 2001 Houston Chronicle report, the region’s transportation plan permitted 195 tons of nitrogen oxide emissions per day. The state’s newer smog plan set the roadway limit at 151 tons. That left a 44-ton daily difference to resolve before projects such as the Katy Freeway widening and new Grand Parkway sections could proceed without a threat to their federal funding.
These were planning limits, not measurements showing how much pollution Houston’s roads produced that day. The question was whether the planned transportation system would fit the state’s clean-air requirements. Environmental groups argued that approving roads under the higher limit would undermine the smog plan’s effort to meet the national ozone health standard. A clean-air plan and a road plan could each have an impressive stack of paperwork behind them and still disagree on the number that mattered.
The calendars helped create the problem. H-GAC—the Houston-Galveston Area Council—adopted its road plan in late 1999. Texas adopted the revised emissions limit in December 2000. As Bill Dawson later explained in his May report, EPA had approved the higher figure before the smog plan was adopted, even though officials knew a lower figure was coming. The two planning schedules had produced incompatible instructions.
02 / The February warning
The risk reached projects before construction
Environmental Defense and the Sierra Club had sued EPA in fall 2000. A court-ordered pause was due to end on the Thursday after Berger’s report, while EPA approval of the state smog plan was expected around April 15. Those approaching dates put an eight-county transportation program at risk. Having a preferred road design or a place on H-GAC’s project list would not settle the emissions dispute.
Berger described the possible consequence as a conformity lapse: the transportation plan would fail to meet the applicable air-quality requirements. Capacity-adding projects without final federal approval could then be stopped from planning, acquiring right-of-way or beginning construction. The delay could start before a contractor arrived with equipment. Atlanta’s federal transportation dollars had been frozen for more than two years beginning in January 1998, providing Houston officials with an uncomfortable example.
The West Loop reconstruction probably would not be endangered, transportation officials said, because it did not add capacity. The Katy Freeway widening belonged on the vulnerable side of that distinction. The proposed work was intended to add lanes, and the photograph beside this article shows how closely the existing main lanes and frontage road sat together between Voss and Campbell. It was taken on May 20, after the settlement, and shows the corridor awaiting change.
03 / February to April 2001
Could Houston keep the roads and lower the emissions?
H-GAC’s chief transportation planner, Alan Clark, argued that the state’s pollution controls, including lower speed limits, could reduce emissions while retaining the planned roads. He also believed the normal eighteen-month adjustment period should give his agency until June 2002 to revise its plan. For planners, the newer limit had arrived after they had prepared the regional program.
For environmentalists, that extra time carried its own risk. Projects started under the existing plan might later need to be dropped from a revised plan to meet the lower limit. Jim Marston of Environmental Defense questioned how much trust the proposed delay required:
“It's not my preference to sue, but that's a pretty significant burden to ask”
The Grand Parkway made a compromise especially difficult. The Sierra Club opposed it because of its effect on urban sprawl; state Senator Jon Lindsay warned that removing it from the plan could end negotiations. The Grand Parkway planning archive shows the larger loop proposal behind that disagreement. Keeping or dropping a project would affect where the region expected to grow, as well as its emissions calculations.
Dawson reported that the argument intensified in April. Environmentalists proposed removing many major road projects and investing heavily in rail and other transit to restart negotiations they considered stalled.
04 / May 10, 2001
May: the stricter limit stayed, the cutoff was avoided
By May 10, Dawson could report a settlement. EPA agreed that local transportation plans must follow the vehicle pollution limit in the latest state smog plan and withdrew its approval of the higher figure. Regional administrator Gregg Cooke explained why that figure could not remain:
“would not lead to achievement of our mutual clean air goals.”
The plaintiffs agreed to drop the suit. Dawson identified four participating groups: Environmental Defense, Sierra Club, Galveston-Houston Association for Smog Prevention, and Galveston Bay Conservation and Preservation Association. A Saturday regulatory deadline was approaching, and the suit could have blocked federal approval of the transportation plan. The settlement removed that immediate threat. H-GAC executive director Jack Steele said it would mean:
“no interruption of planning or funding for any transportation projects”
Harris County Judge Robert Eckels emphasized that local officials would retain control of transportation planning. The environmental plaintiffs retained the right to activate another related lawsuit, although attorney Jim Blackburn expressed confidence that further litigation could be avoided.
The region could keep planning its roads, but the calculations now had to fit the 151-ton daily limit.