Houston’s Light-Rail Court Battle in 2001

A temporary injunction stopped Metro’s starter line before construction contracts were awarded. Three reports follow the delay and the appellate ruling that allowed work to proceed.

THE HISTORICAL CONTEXT Reporting from February and March 2001
Elevated I-45 traffic on the western side of downtown Houston, with the skyline filling the background.↗ Enlarge

Collection: TexasFreeway Houston freeway photographs

Downtown beside I-45 · July 2001

I-45 on the western side of downtown21-July-2001

I-45 passes the downtown skyline on July 21, 2001. This related archive photograph shows the city setting for the rail debate; the proposed Main Street line is not visible.

Original image caption

A. Interstate 45 on the western side of downtown, looking south. 21-July-2001.

Explore downtown Houston freeway photographs →

TexasFreeway commentary · Selected passages from separately credited Houston Chronicle reports appear in quotation panels. The surrounding narrative interprets the decisions and conditions of February and March 2001.

01 / February 4, 2001

February: a starter line stopped at the contract table

Houston’s light rail project was close enough to construction that Metro expected to award more than $200 million in contracts. Then a court order changed the agenda. Ed Asher’s February 4, 2001 Houston Chronicle report described a board meeting that was supposed to advance the 7.5-mile line from downtown to Reliant Park. Instead, board members would meet with their attorney to discuss what they could do next.

“This was the heart of the rail system that was set to be awarded. Now, I can't tell you what's going to happen”

Julie H. Gilbert, Metro communications and marketing vice president, quoted by Ed Asher in the Houston Chronicle, February 4, 2001

State District Judge John Devine had issued a temporary injunction on February 2. Councilman Rob Todd’s suit argued that Houston’s City Charter required a public vote before the project could proceed. City Council had permitted the line to use city streets; Todd challenged the city’s and Metro’s decision to proceed without an election. The March report identified that permission as an 11–4 council vote on November 21, covering segments of Main, Fannin and San Jacinto streets. The city and transit agency argued that the law required no such referendum.

The planned $300 million line had been deliberately sized as a starter system that would not need a bond referendum. Earlier rail votes supplied a difficult backdrop: voters rejected a rail bond proposal in 1983, approved a Metro spending package including rail in 1988, and then elected Bob Lanier, who had campaigned partly on stopping it. The new plan avoided borrowing that would trigger a bond election. The fight had shifted to permission to use streets.

02 / February 5, 2001

February 5: design continued, construction waited

Mike Glenn’s February 5 report followed the board’s response. Metro withdrew more than $130 million in rail-related construction contracts, including five line segments and utility relocations. Glenn reported the contracts withdrawn at Monday’s meeting; Asher had reported more than $200 million expected to be awarded. Neither report supplied an itemized comparison of the two totals.

Board chairman Robert Miller said the lost start date prevented Metro from meeting its intended 2004 Super Bowl schedule. Design could continue, but its relationship to construction had changed. Work that Metro had expected to overlap would now take longer overall.

“We were going to do construction and design simultaneously”

Robert Miller, Metro board chairman, quoted by Mike Glenn in the Houston Chronicle, February 5, 2001

Miller estimated that delay would cost about $2 million a month. Bid prices were protected for ninety days, giving Metro a limited period to get contracts moving before possibly rebidding at higher prices. The injunction also stopped $11.2 million in Fannin improvements. A legal dispute about rail permission had reached street work, utility contracts and the agency’s construction schedule.

Todd urged an election as the remedy. His lawyer, Allan Parker, emphasized the public’s authority over expensive work that would disrupt streets. Metro argued that it was a legislatively created government agency with council permission, rather than a commercial franchise seeking a special privilege. Miller worried that the ruling’s logic could affect other Metro street and road work too.

03 / March 8, 2001

March: the appeals court rejected the injunction

On March 8, Rad Sallee reported a unanimous decision by a three-judge panel of the 1st Court of Appeals allowing Metro to move forward. The petition dispute was central. Opponents had collected about 1,100 signatures and argued that the charter threshold for a vote had been met. Metro and the city said more than 20,000 were required, and the panel agreed.

The opinion, written by Justice Margaret Mirabal, concluded that Devine had misapplied the law. It overturned the injunction and sent the case back to his court for action consistent with the appellate ruling.

“erred in application of the law to the undisputed facts”

The appellate opinion, quoted by Rad Sallee in the Houston Chronicle, March 8, 2001

Metro planned a board meeting to restart the held contracts, followed by a ceremonial groundbreaking. Chief executive Shirley DeLibero estimated the six-week delay had cost taxpayers about $3 million. Opponents, meanwhile, argued that preventing the project could save much more.

City and Metro attorneys viewed the ruling as strong grounds to proceed. Yet Sallee explicitly reported that the case had not been finally disposed of, and Todd’s attorney planned an appeal. The court had removed the obstacle to construction. That did not mean every legal avenue or political argument had ended.

04 / The March outlook

A construction opening, with the larger rail question ahead

Sports officials wanted rail to connect venues, and Mayor Lee Brown linked effective transit to Houston’s hopes for the 2012 Olympics. Those were period ambitions. By March, Metro still considered completion before the 2004 Super Bowl unlikely. The ruling let the agency resume contracts, but it could not give back the weeks already lost.

The downtown Houston photographs show the city’s freeway setting later in 2001, with elevated I-45 beside the skyline. Metro’s plan asked an existing street corridor to take on another transportation role within this freeway-ringed downtown.

Miller repeated Metro’s promise to put any extensions before voters. Elsewhere, the Westpark corridor photographs recorded land intended to remain available for a potential future rail line. That separate proposal was not an extension approved by this court decision. It illustrates why permission for one 7.5-mile starter route could not settle Houston’s larger rail plans.