HOUSTON ARCHIVE · COMMENTARY
Houston’s 2001 Air Plan: 55 mph and a Promise of Cleaner Air
July’s proposed approval became an October signing, with lower highway speeds, tougher exhaust tests and major industrial cuts still ahead.
↗ EnlargeCollection: TexasFreeway Houston photographs
Sam Houston Tollway · May 2001
The trench south of Memorial20-May-2001Cars travel through the Sam Houston Tollway’s trench south of Memorial in this May 2001 view. The photograph predates the two air-plan reports and shows the kind of established roadway where motorists would encounter the announced driving changes.
Original image caption
(high resolution 217k) Looking north from south of Memorial. The freeway is in a trench through this area. This is the only sustained depressed section of the Sam Houston Tollway. 20-May-2001.
TexasFreeway commentary · This combined account interprets two 2001 Houston Chronicle reports. Selected passages appear in attributed quotation panels.
01 / July 10, 2001
July: approval was proposed, with work still unfinished
For Houston drivers, the most visible parts of the proposed clean-air program would be a lower number on the speed-limit sign and a tougher annual inspection. Those everyday changes belonged to a larger Houston–Galveston effort that also required major industrial pollution cuts and aimed to meet clean-air goals by 2007.
In Matt Schwartz’s July 10 Houston Chronicle report, EPA had proposed approving seven parts of the plan, including the overall demonstration of how the region would meet those goals. Regional administrator Gregg Cooke acknowledged that some components were still being finalized. A public-comment period would follow publication of the proposal in the Federal Register.
Environmental Defense Fund official Mark McLeod wanted specific reduction measures written into the plan, even if their implementation came later. State officials instead offered legally binding promises to supply additional measures in the future. To a business facing new rules, that flexibility could make room for a better solution. To someone counting pollution reductions, it left part of the calculation dependent on decisions still ahead.
“It does give us some flexibility. But it does say that you have to get it done.”
McLeod pointed to an actual change in approach: opposition to morning restrictions on construction equipment had prompted legislative alternatives, including incentives that EPA appeared to favor. He wanted detailed measures in place so those who disliked them would have a reason to develop workable alternatives.
02 / October 16, 2001
October: 55 mph limits and tougher exhaust tests
Tony Freemantle’s October 16 report recorded the next step. Cooke had signed the plan the previous day, with Governor Rick Perry, Mayor Lee Brown and other officials present. Federal approval now covered a program with specific changes planned for drivers, industry and other engine operators.
Freemantle reported that highway speed limits would fall to 55 mph by the following May, meaning May 2002. Drivers would also face a stricter, more expensive annual tailpipe-emissions test. Those measures would bring the regional program into everyday travel: one would change the permitted speed on a trip, and the other would change the test a vehicle had to pass.
The May 2001 Sam Houston Tollway photograph shows cars spread across the lanes below Memorial’s surrounding ground level, shortly before the air-plan reports. The West Loop photographs put the same discussion beside the Westheimer overpass and nearby buildings: familiar road settings for a program that would ask more of motorists.
03 / The wider program
The clean-air plan reached well beyond private cars
The driver’s inspection was only one part of the package. Freemantle described an average 90 percent nitrogen-oxide reduction requirement for major industrial sources in the eight-county region by March 31, 2007. The plan’s overall expected reductions covered a wider range of sources: 75 percent for nitrogen oxides and 40 percent for volatile organic compounds by 2007.
The reporting explained the connection to smog: nitrogen oxides and volatile organic compounds combine with sunlight to form ozone. A plan addressing those ingredients had to reach more than the exhaust of passenger cars. Its provisions included cleaner diesel for on-road and off-road vehicles along and east of I-35, limits on excessive idling by large commercial trucks, and a regional nitrogen-oxide cap with banking and trading below it.
Commercial lawn-equipment operators faced a change to their working hours: a ban on gasoline-powered equipment between 6 a.m. and noon, from April 1 through October 31, scheduled to start in 2005. July’s report also discussed cleaner airport ground-support equipment and rules for large spark-ignited engines. Construction machinery, trucks, industrial plants and airport operations were all part of the same effort. Reducing a posted highway speed would be easy to see; much of the plan depended on equipment and operations away from the main lanes.
04 / Implementation ahead
Approval left a disputed emissions gap to close
The sharp disagreement concerned reductions that had yet to be specified. In October, Environmental Defense’s Jim Marston said legal challenges and lobbying had weakened parts of the plan, leaving a gap of 56 tons per day of nitrogen oxides. He said at least 13 lawsuits had challenged various aspects. State officials maintained that binding future commitments, new technology and federal fuel standards would close the gap.
Cooke pointed to a 2004 midterm review as a way to address deficiencies, and said a quarter of the enforceable commitments had to be in place by May 1 of that year. The review provided a scheduled opportunity to adjust the program, with compliance still the goal for 2007.
“We are not there yet, but we are clearly on the right course.”
Cooke had described the health concerns in everyday terms, pointing to schoolchildren and older residents who should avoid being outside at certain times on bad-air days. That gave the promised reductions a purpose beyond passing an inspection. At the signing, Texas Natural Resource Conservation Commission chairman Robert Huston called implementation the difficult part. The disputed emissions gap made that a substantial job even with an approved plan.