Grand Parkway in Spring: The Old Route Gets the Applause
Nearly 1,000 people packed a church meeting in March 2001. Alternative routes threatened plans already under way for churches, a school and a water plant.
↗ EnlargeCollection: TexasFreeway Houston photographs
The existing west segment, seen in July 2001.
D. South from WestheimerJuly 20, 2001Trees and a broad median frame the Grand Parkway south of Westheimer in July 2001. This separate Segment D view shows the physical scale of an existing parkway section, south of the Spring-area Segment F alternatives discussed here.
Original image caption
(high resolution 164k) D. This view looks south from the Westheimer overpass. The wooded area in the background is along Buffalo Bayou, which is close to its original headwaters in this region. Photo taken 20-July-2001.
TexasFreeway commentary · Selected, attributed excerpts retain the newspaper’s original words. The surrounding narrative is new analysis.
01 / March 2001
One option won applause at Spring Tabernacle
David Gornet expected no standing ovation when he faced the overflow crowd at Spring Tabernacle Church. Nearly 1,000 people had come to discuss Grand Parkway route changes in northwest Houston. They did applaud one thing: an alternative following the route that had appeared on maps for years. At a meeting about change, the old line was the welcome news.
Carol Christian’s March 17, 2001 report described residents who generally supported the parkway but objected to placing it along FM 2920 or Spring Stuebner. The historical proposal had run roughly two miles north of Spring Stuebner. Moving a freeway closer to established community facilities could shift the costs of the project onto people who had planned around the earlier map.
Gornet described the fourth alternative as running west from David Wayne Hooks Memorial Airport, crossing Kuykendahl and Spring Stuebner, then proceeding east to I-45. Although he called it a new alignment, Christian identified it as the historical alignment. It was being offered for equal study with the other three options. Applause did not make it the selected route.
“This will be studied in equal detail to the other three you will not clap about”
02 / Spring Stuebner and FM 2920
The churches and water plant had their own plans
Spring Tabernacle had started work on a $6 million complex beside its building. The Rev. C.G. Green said one alternative would cross church property. His objection was specific: the church had planned around FM 2920’s existing location. A new road through that property could affect an investment already under construction, rather than merely limiting an idea for future development.
Ken Martin, representing St. Edward’s Catholic Church on Spring Stuebner, said two options would pass near the school. He raised noise and dust. Those were concerns about the proposed location, not measured effects from a completed freeway. They nevertheless showed why counting affected parcels alone would miss part of the issue. A school could be close enough to experience the project even without sitting directly in its path.
The Bridgestone Municipal Utility District was renovating one of its water plants for $1.5 million. Board member Skip Warren said the alternatives would interfere with that work and that nobody had consulted the district. For a highway planner, these were route alternatives. For the organizations already spending money there, they were possible changes to projects that had moved beyond the alternative stage.
03 / A proposed Union Pacific yard
Avoiding a costly bridge moved the problem elsewhere
Gornet explained why the association was considering changes: the historical path would require a 4,000-foot elevated bridge over a proposed Union Pacific rail yard. That was a substantial additional structure. The audience’s response nearly drowned out his discussion of the expense. Their reaction did not make the engineering issue disappear; it made clear that reducing the highway’s cost could create other costs nearby.
An alternative avoiding that bridge could affect church property, school surroundings or a water plant. Keeping the historical route could require the long railway crossing. The meeting brought those consequences into the same room. The sensible comparison needed both the highway structure and the community investments, rather than treating one set as real money and the other as background opposition.
The broader Grand Parkway planning account records the northern route controversy alongside the different problems facing southwest Segment C and the already built west segment. The later west photographs should be read as context for the size of a parkway corridor, not as pictures of the Spring alternatives.
04 / Period forecasts
Residents had time to argue, but needed a route they could plan around
Gornet’s timetable put the earliest design completion for Segment F in August 2002 and the earliest construction start in November 2003. Those were conditional planning dates given in March 2001. The association coordinated the route and right-of-way work, while TxDOT and the Federal Highway Administration would have the final say. The church meeting itself could neither authorize construction nor promise which property would be spared.
The existing 19-mile Segment D was still the loop’s only completed section. Much of the rest remained under discussion, including a prairie crossing farther west. In Spring, the immediate request was more concrete than approval or rejection of a 170-mile loop: examine the familiar alignment as seriously as the new alternatives. The applause marked support for having that choice examined; the property questions remained open.