Future section of US 90, the Northeast/Crosby Freeway

The 2001 account follows the planned US 90 link from the I-10 and Loop 610 interchange to Beltway 8, including the period schedule and the unfinished roadway waiting at both ends.

Last updated 28-May-2001

Period Houston freeway map highlighting the planned US 90 construction between Loop 610 and Beltway 8.

TexasFreeway Houston planning archive

The 2001 map marks the missing freeway segment between Loop 610 and Beltway 8.

Crosby Freeway extension location

From the Houston archive. This account retains its original wording and describes plans, funding and expected construction dates as they stood in May 2001.

01 / MAY 2001 ACCOUNT

The missing section inside Beltway 8

Also see: Views of existing Crosby Freeway

The US 90 freeway on the northeast side of Houston has been on Houston's official freeway plans since the mid 1950's. The roadway outside of Beltway 8 was upgraded to a freeway in the 1980's. However, this section of Houston remains largely undeveloped, so construction of the freeway inside Beltway 8 has not been a high priority. Well, things will start to happen soon. Contracts will be awarded starting in 2002 to build this freeway, which historically was known as the Northeast Freeway, but is now designated as the Crosby Freeway.

02 / PERIOD TIMELINE

Freeway History

Crosby Freeway history
1955The first official Houston Transportation Plan with freeways officially included, published in 1955, shows the Crosby Freeway as a "proposed addition"
1959The 1959 Plan for Major Thoroughfares and Freeways shows the officially adopted location of the Northeast Freeway, which is identical or very close to the actual constructed route.
Early 1970'sThe IH-610/IH-10 4-level interchange is constructed with provisions for connections to the future US90 freeway.
1980'sAbout 10 miles of roadway east of Beltway 8 is upgraded to a freeway. The overpass at Beltway 8 is constructed but remains closed to traffic. (See photo.)
2002Construction will finally begin on the freeway inside Beltway 8

03 / 2001 TXDOT PROGRAM

Construction Schedule

Information is from the 2001 TxDOT Unified Transportation Plan and is subject to change.

Crosby Freeway construction schedule
DescriptionAward DateStatusCost, millions
Interchange at IH-10/IH-6102002Approved$33
0.9 mile section of freeway2003Approved$11.5
2.9 mile section of feeder roads2004Approved$7.4
3.1 mile section of freeway-Unfunded$33.8

04 / 1996–2001 PHOTOGRAPHS

Views of the planned connection

Unfinished US 90 connection stub beside the I-10 and Loop 610 interchange.

TexasFreeway Houston archive

May 22, 2001

Future US 90 connection at I-10 and Loop 610

This view shows the stub-out for the connection to the Northwest Freeway on the existing ramp from northbound IH-610 to eastbound IH-10. Motorists have seen this stub-out for about 30 years. Photo taken 22-May-2001.

(high resolution 141k)

Aerial view of the East Loop and I-10 interchange showing future US 90 connection provisions.

TexasFreeway Houston archive

Around 1996

East Loop and I-10 interchange

Aerial view of the interchange at the East Loop and IH-10, which was constructed in the early 1970's. If you look closely you can see the stub-outs and embankment for the future connections to the Northeast/Crosby Freeway, which will begin at this interchange. Construction on the connections to the future Northeast Freeway is scheduled to begin in 2002. This aerial view was taken around 1996.

Westward view from the end of the US 90 freeway near Beltway 8 in summer 2000.

TexasFreeway Houston archive

Summer 2000

West end of the US 90 freeway at Beltway 8

This is the current end of the US90 freeway west of Beltway 8. This view looks west. Photo taken summer 2000.

Eastward view of the unused US 90 freeway section crossing Beltway 8 in summer 2000.

TexasFreeway Houston archive

Summer 2000

Unused US 90 freeway section across Beltway 8

This view shows the section of freeway that crosses Beltway 8. The traffic light in the background is the Beltway 8 feeder road. Constructed in the 1980's, it has been closed traffic and has been derelict. It will be another 5-10 years before motorists will be able to drive on this section of freeway. This view looks east. Photo taken summer 2000.