Trinity Parkway in 2000: The Price Rose. The Funding Didn’t.

A $669 million estimate put Dallas’s preferred river road close to the price of rebuilding Central Expressway. Toll revenue and city bonds would cover only part of it.

THE HISTORICAL CONTEXT Reporting dated
I-30 lanes curve through a trench beneath downtown Dallas bridges in September 2000.↗ Enlarge

Collection: TexasFreeway archive

The traffic was here. The alternate route was still on paper.

The I-30 canyonSeptember 2000

I-30 south of downtown Dallas in September 2000. Traffic curves through a trench beneath the cross streets, showing the established freeway network that the proposed Trinity Parkway was intended to relieve.

Original image caption

Interstate 30 on the south side of downtown Dallas. This freeway is in a trench. All lanes shown in the photograph are freeway lanes. (The outer lanes are not feeders.) This freeway was constructed around 1960.

Explore the September 2000 downtown Dallas photographs →

TexasFreeway commentary · A look back at the decisions, tradeoffs and people behind the road. Newspaper excerpts are credited beside each quotation.

01 / The new estimate

The Trinity Parkway had a Central Expressway-sized price

Dallas’s proposed river road had acquired a price tag large enough to invite a familiar comparison. In November 2000, the preferred Trinity Parkway alignment was estimated at $669 million. Rebuilding 9.3 miles of North Central Expressway had cost about $680 million, including land, utilities and construction. A reliever road around downtown was approaching the cost of one of the region’s most substantial freeway rebuilds.

Victoria Loe Hicks and Tony Hartzel reported the new figures on November 11, after a study summary reached the City Council. The preferred road would have four lanes on each side of the river, inside the levees. Its previous estimate was $439 million. The increase was $230 million, before Dallas had settled how to pay the earlier amount.

The September 2000 I-30 photograph shows part of the existing downtown freeway system the proposal was intended to relieve. The preserved downtown archive notes describe why officials were looking for an alternate route.

02 / The funding gap

A toll road still needed a large public contribution

Dallas voters had approved $84 million for the road in 1998. The North Texas Tollway Authority estimated that preliminary traffic and toll projections could support another $150 million in bonds. Against the preferred $669 million design, those two amounts left $435 million to find. Calling it a tollway did not make the remaining bill disappear.

The expectation was that TxDOT would fill the gap. District engineer Jay Nelson described an agency already unable to fund most of its identified projects. He had not yet seen the revised Trinity figures, so his comments were a statement of the state’s constraints rather than a rejection of this particular estimate.

“But ... if you can't come up with the funds, you have to reduce what you want to do.”

Jay Nelson, quoted by Victoria Loe Hicks and Tony Hartzel, The Dallas Morning News, November 11, 2000

That left Dallas with practical choices: seek more money, wait for it, build less, or combine those approaches. Each choice could change what drivers and park visitors would eventually get.

03 / Speed and access

The parkway’s new speed brought new access costs

The cost increase was not simply an unexplained engineering surcharge. The study summary identified park-access ramps and tunnels, improved I-35 connections in Oak Cliff, retaining walls, landscaping and toll plazas. Some of the bill came from making a large highway fit beside the park it was also supposed to serve.

The earlier concept had been a 45-mph parkway with direct access to a downtown park and lake. The tollway authority concluded that this slower road would not generate enough revenue, and the design became a 60-mph limited-access highway. A faster route could attract through traffic, but access to the riverside destination now required additional arrangements.

Deputy director Katie Nees suggested removing some interstate ramps or park access roads, or starting with six lanes instead of eight. Those were possible savings with consequences: fewer connections or fewer lanes would mean a different facility, not the same one bought more cheaply.

04 / The alternatives

The cheaper alignment did not settle the river debate

Halff Associates evaluated five alignments, ranging from $620 million for eight lanes inside the east levee to $1.2 billion for an elevated freeway along Industrial Boulevard. A surface Industrial route was estimated at $923 million; opponents said that corridor could displace as many as 178 businesses. Inside the levees, critics raised flooding and green-space concerns.

The Trinity planning account brings these alternatives together with a route map and the site’s contemporary reaction to the $435 million funding gap: “Ouch.” That was a fairly economical response to a very expensive problem.

The November 15 follow-up report described Mayor Ron Kirk’s argument that the lake and trails should proceed while the road’s financing remained unsettled. By June 2001, an economic consultant would also question whether the faster road best served the park’s neighbors. The growing estimate had opened questions about the project’s purpose as well as its price.

Original TexasFreeway link note · November 2000

Also see a follow-up article published 15-Nov-2000.