Southwest Parkway in 2001: Fort Worth Needed to Keep Its Funding
Fort Worth had money earmarked for Southwest Parkway and decades of planning behind it. In October 2001, officials warned that keeping the project moving could determine whether that support lasted.
↗ EnlargeCollection: TexasFreeway archive
Downtown’s new ramps were rising. Southwest Parkway was still being planned.
Looking east over the stack construction zoneSeptember 4, 2000Cranes and unfinished ramps mark the Fort Worth Mixmaster on September 4, 2000. This separate I-30/I-35W project provides a period view of the downtown area the proposed parkway would serve; it does not show Southwest Parkway construction.
Original image caption
Looking east over the stack construction zone. The new freeway is nearly complete (see photo below), with the opening awaiting the completion of the interchange.
TexasFreeway commentary · A look back at the decisions, tradeoffs and people behind the road. Newspaper excerpts are credited beside each quotation.
01 / Keeping the funding
Southwest Parkway needed someone to move it forward
After more than 30 years of planning, Fort Worth was looking for a project manager. That sounds like a modest step for a road intended to connect downtown with the southwest side and eventually Cleburne. By October 2001, however, local officials were worried that delay could cost the proposed Southwest Parkway its funding.
Anna M. Tinsley’s October 17 Star-Telegram report described a City Council effort to hire a person or team to coordinate the work. Councilman Chuck Silcox wanted the city to demonstrate that it could advance the project while other North Texas roads competed for the same limited money.
“There's a chance down the road we could lose funding because there's other projects.”
The warning was about money already identified for a project that still needed considerable preparation. Support from transportation officials could help, but the city also had to organize the work and keep the next decisions moving. A familiar name on a regional plan was no guarantee of a construction contract.
02 / The toll road plan
The Fort Worth proposal combined toll road and highway
Tinsley reported $230.4 million earmarked from several transportation sources. Estimates nevertheless reached as high as $284 million, including up to $38 million for right of way. Those figures explain why officials could describe substantial funding and still worry about getting the road built.
The proposed four-lane facility covered 15.1 miles, with 8.4 miles of toll road and 6.7 miles of highway. This was the Fort Worth portion of a broader corridor planned toward Cleburne.
A probable $1 toll would help repay construction bonds and cover landscaping and maintenance. Toll financing meant that future users would contribute to paying for the facility. It also meant the project needed a credible financial plan, rather than simply a place on the city’s wish list.
Donations could reduce the city and state’s costs, officials said. That possibility was particularly relevant to acquiring land. It was a potential saving, with no final donation total reported, and therefore no basis for treating the gap between earmarked money and estimated cost as settled.
03 / Review and schedule
Environmental review still stood before construction
Transportation officials were preparing an environmental impact statement covering effects such as air and water quality. They expected to submit it for federal review by the end of 2001, with public hearings the following summer. Another hearing was planned for November to update residents.
The hiring decision therefore came during a period of studies, coordination and public discussion. The report did not describe an environmentally cleared project ready for bulldozers. Engineering consultant Darrell Thompson forecast a spring 2004 construction start and roughly two years of work.
The preserved SH 121 route-status account also anticipated a 2004 start for Southwest Parkway. Reading the two together gives a useful view of the expectations circulating at the time: a road regarded as likely to proceed, with several years of preparation still ahead.
04 / The downtown connection
Southwest Fort Worth wanted a more direct trip downtown
Thompson described the everyday purpose plainly. The road would help southwest Fort Worth residents get to and from downtown and relieve traffic on Hulen, Forest Park and Bryant Irvin. For people relying on those streets, the proposal offered a more direct trip into downtown—once someone could get it built.
Downtown itself was changing. The September 2000 Mixmaster photograph shows cranes and unfinished elevated ramps during another major freeway project. It gives the proposed parkway’s downtown destination a period setting, while showing construction on I-30 and I-35W rather than Southwest Parkway.
Fort Worth could have a large interchange taking shape and another major road still searching for a coordinator. For the parkway, the immediate job in October 2001 was to turn sustained political support into completed preparations while the funding was still available.