SH 360 in 2001: Six Miles of Freeway, Several Different Problems
An Arlington corridor study considered additional lanes, rebuilt interchanges and smaller improvements. The difficult part was matching each solution to the places where traffic actually slowed down.
↗ EnlargeCollection: TexasFreeway archive
SH 360 runs beneath the stack at the study’s southern end.
I-20 and Texas 360September 2000Looking north at SH 360 beneath I-20’s connector ramps in September 2000. This is the southern boundary of the later Arlington study, not the I-30 or Division Street junctions proposed for reconstruction. The photograph records one moment rather than peak-period traffic.
Original image caption
This view looks north with the 360 lanes at ground level. Notice how this stack does not use the cookie-cutter "T" center pier. This stack must be newer than the others, as it appears not to have come from the same design shop.
TexasFreeway commentary · A look back at the decisions, tradeoffs and people behind the road. Newspaper excerpts are credited beside each quotation.
01 / The Arlington commute
SH 360 congestion was changing the working day
Rea Norrell left southeast Arlington for work in Irving by 6:45 a.m. and rarely tried the return trip before 6 p.m. She told the Star-Telegram that she did not need those extra hours at work. They were her way of dealing with congestion on SH 360.
J. Taylor Rushing’s August 3, 2001 report put a recognizable trip beside an engineering study. State figures showed that the 6.2-mile section between I-20 and I-30 could take up to 14 minutes at 7:30 a.m., with traffic unable to exceed 30 mph during the busiest periods.
“Traffic always stacks up at the same places, and I've already tried other roads.”
Norrell’s account explained why a short freeway could have a large effect on someone’s day. The delay was recurring enough to influence when she left home and work. Adding pavement was one possible response, but the planners also had to examine the particular junctions where queues formed.
02 / Three different jobs
I-30, Division Street and the main lanes needed separate attention
The corridor study identified three main jobs. At I-30, officials considered replacing the cloverleaf with a more elaborate network, using the I-820/I-30 junction as a comparison. The reported estimate ranged from $170 million to $260 million.
Division Street was the largest bottleneck identified by the studies. Its potential reconstruction involved ramps, railroad bridges and frontage roads, at an estimated $98 million to $131 million. That is a useful reminder of how much can occupy one highway crossing: a ramp change may have consequences for the railway and local streets beside it.
Widening the freeway formed the third category. Ideas included HOV lanes and as many as 12 general-purpose lanes, with estimates ranging from $28 million to $199 million. Rushing also described a ten-lane option with an HOV lane. These were alternatives under discussion, not one selected cross-section.
The cost ranges cannot simply be added and called an approved budget. Different designs were still being considered, and planners had not settled on a final combination. Smaller measures, including expanded park-and-ride lots, remained part of the discussion alongside expensive reconstruction.
03 / A public study
Arlington’s SH 360 plan was still being assembled
About 60 people attended the public meeting at the La Quinta Inn on SH 360. TxDOT and its consultant, Halff Associates, were gathering ideas before a later meeting narrowed the choices. Residential, business, environmental and civic representatives from Arlington, Fort Worth and Grand Prairie were involved.
Funding responsibilities also crossed jurisdictional lines. Federal and state money would cover highway and interstate work, while local funds would be needed for arterial streets such as Division and Abram. A corridor plan therefore depended on agreement about nearby roads as well as the freeway.
The timetable was long even if those agreements came together. Consultant Martin Molloy anticipated approval of a final plan in late 2002, followed by two years of design and possible land acquisition. Construction might begin in 2005 and take five years. For Norrell, encouragement about the study came with impatience about the pace.
04 / The corridor photographs
The SH 360 photographs cover different pieces of the road
The September 2000 view at I-20 looks north through the stack, with SH 360’s main lanes at ground level beneath several ramps. It records the southern end of the studied stretch. The lightly trafficked instant in the photograph cannot tell us what the weekday commute looked like farther north.
The SH 360 airport collection follows another section entirely, from SH 183 to SH 121. In May 2001, much of that northern corridor still consisted of frontage roads. Its preserved construction schedule concerns filling in main lanes there, rather than rebuilding the Arlington section between I-20 and I-30.
Together, the accounts show why a road number alone is a poor guide to a project’s scope. On one part of SH 360, planners were studying an overburdened freeway. On another, the archive was documenting space reserved for a freeway that was still incomplete.