SH 121 in 2001: A $22 Million Land Award Put the Freeway Plan Under Pressure

A dispute over 38 acres in The Colony threatened both the construction schedule and the road design. It also raised questions about a consultant working for the county and the landowner.

THE HISTORICAL CONTEXT Reporting dated
A truck approaches overhead traffic signals on the wide divided SH 121 road south of the Lewisville bypass.↗ Enlarge

Collection: TexasFreeway archive

A route still interrupted by traffic lights.

Traffic light south of the Lewisville bypassSeptember 2000

This September 2000 view is south of the Lewisville bypass, elsewhere on the corridor. It illustrates the signalized road stage and does not show the disputed property in The Colony. The original funding caption describes its earlier moment.

Original image caption

Just south of the Lewisville bypass, there is still a traffic light. Main freeway lanes are a high priority, but funding is awaiting the completion of the major study of the Funnel.

Explore the Lewisville bypass photographs →

TexasFreeway commentary · A look back at the decisions, tradeoffs and people behind the road. Newspaper excerpts are credited beside each quotation.

01 / The land award

Thirty-eight acres unsettled the SH 121 schedule

A freeway project can have its financing arranged and still run into trouble buying the ground beneath it. In November 2001, a $22 million award for 38 acres of pasture in The Colony brought that problem into sharp focus on SH 121. State officials said construction could slip six months or more from the expected early-2003 start.

Brooks Egerton and Reese Dunklin reported that the land belonged to the Maharishi Global Development Fund. The award was about $11 million above the state’s final offer. The state wanted to appeal, and the fund also planned an appeal because its appraisers considered the land worth more. Neither side treated the commissioners’ decision as a satisfactory ending.

The award was about five times the fund’s purchase price per acre the year before. That comparison made a striking headline, but it did not settle the valuation dispute. Two commissioners said their decision followed the hearing evidence; one cited an appraisal of $27 million and described the award as a middle position.

02 / The design at risk

The land cost could change exits and frontage roads

TxDOT deputy district engineer Bob Brown said the cost would require redesign near the property. Possible cuts included fewer exits and narrower frontage roads, or removing frontage roads altogether. That gave the dispute a consequence beyond the amount paid to a landowner: a revised design could change how people reached nearby properties.

Brown also expected the decision to affect other acquisitions along the route:

“the judgment on this tract will affect judgments on other tracts along Highway 121.”

Bob Brown, quoted by Brooks Egerton and Reese Dunklin, The Dallas Morning News, November 22, 2001

His warning concerned the total cost of assembling a highway corridor. If other awards rose, the budget pressure could extend beyond these 38 acres. The fund’s real estate lawyer, Richard Hayes, challenged the state’s account, calling its delay warnings posturing and pointing to other condemnation cases that he said had produced no delays.

The report left those positions in disagreement. It did not establish that the redesign had been chosen, that the appeals had been decided or that the forecast delay actually occurred. The meaningful news was that state engineers were considering changes to the road itself while the land-price fight continued.

03 / The competing roles

One consultant had worked for both sides

John Polster’s firm was receiving about $30,000 a month from Denton County to advance SH 121 and other major roads. Its duties included arranging financing, hiring contractors and pressing owners to settle right-of-way matters. Polster had also worked for the Maharishi fund, putting his two clients on different sides of this acquisition.

He said he was leaving the fund’s work because County Judge Scott Armey was concerned about a perceived conflict. Polster, Armey, Commissioner Sandy Jacobs and the district attorney’s office maintained that there was no actual conflict. Some commissioners disputed how much they had known about the arrangement. County officials defended the arrangement even as questions about it complicated an already bitter land dispute.

Armey also faulted TxDOT’s land valuations, saying appreciation had outpaced estimates while the county sought donations over many years. Jacobs defended Polster and credited local officials with advancing construction. A plan promoted as a way to build sooner was now being tested by the expense and difficulty of obtaining its right of way.

04 / The road people needed

The Colony still faced traffic lights and a growing queue

The existing road between The Colony and the Dallas North Tollway had a series of traffic signals. The most recent regional count cited in the report put traffic at about 48,000 vehicles a day in 1999. Mayor Bernetta Henville-Shannon wanted the promised relief and said she would hold Jacobs to an assurance that the project would not be delayed.

The earlier traffic-light photograph south of the Lewisville bypass shows another signalized part of SH 121. It gives the waiting-for-main-lanes story a recognizable setting, while leaving the disputed tract in The Colony unidentified. The photograph dates from September 2000; its caption’s funding description belongs to that earlier period.

The August bypass-funding announcement had already laid out engineering, utility and land-acquisition deadlines before bidding. November’s dispute shows how one of those preparations could threaten both the schedule and the planned access to the road.