Dallas–Fort Worth / Construction archive
SH 114 Construction West of DFW Airport
May 14, 2001 · Historical photographs
In May 2001, SH 114 ended at Southlake Boulevard while work pushed west through graded right-of-way and new overpasses. Seven photographs follow the project from the freeway end to the untouched stretch between Dove Road and Kimball.
↗ EnlargeA freeway taking shape west of Southlake.
May 14, 2001 · 7 photographs
SH 114 construction west of Southlake
Photos taken May 14, 2001.
↗ EnlargeThe freeway end at Southlake Boulevard
(high resolution 151k) Looking west at the current end of the freeway at Southlake Boulevard. Construction can be seen just on the other side of the overpass.
↗ EnlargeLooking west from the Southlake overpass
(high resolution 293k) Looking west from the Southlake overpass.
↗ EnlargeWest of Southlake, looking west
(high resolution 191k) Looking west from west of Southlake.
↗ EnlargeWest of Southlake, looking east
(high resolution 141k) Looking back eastward towards the Southlake overpass.
↗ EnlargeThe new overpass at Kimball Road
(high resolution 159k) The new overpass at Kimball road.
↗ EnlargeThe Dove Road overpass
(high resolution 159k) Looking east at the Dove road overpass, which is about 2-3 miles west of Kimball.
↗ EnlargeThe corridor between Dove Road and Kimball
(high resolution 138k) Between Dove Road and Kimball, construction has not yet begun. About $36.5 million in contracts will be awarded in summer 2001. The right-of-way will be substantially widened to about 400 feet (122m). Displacements will be minimal since most of the land in the corridor is vacant.
Historical archive · 1 map
Route map
Texas 114 Construction West of DFW Airport, May 2001
Go to 114 main page
In May 2001, there was $40.4 million work in progress, about 70% complete.
An additional $36.5 million in contracts will be awarded in summer 2001 to complete this section of freeway.
↗ EnlargeSH 114 construction location map
SH 114 construction location map