Dallas–Fort Worth / Photo archive
President George Bush Turnpike
September 2000 · Historical photographs
Seven September 2000 views trace the Bush Turnpike from Garland toward the Dallas North Tollway. The original account tells how a road nearly cancelled in the 1980s finally took shape—and records the expansion plans still ahead in 2001.
↗ EnlargeAcross the northern suburbs.
September 2000 · 3 photographs
Garland and the US 75 interchange
All photos taken September 2000
Also see: Driver's view of the full 190 corridor, August 19, 2001.
↗ EnlargeThe SH 78 beginning
↗ EnlargeFirewheel section
↗ EnlargeUS 75 stack
September 2000 · 4 photographs
US 75 to the Dallas North Tollway
↗ EnlargeUS 75 from the south
↗ EnlargeBetween US 75 and the Tollway
↗ EnlargeDallas North Tollway stack
↗ EnlargeThe Tollway interchange from the south
September 2000 · 1 photographs
Route references
SH190, President George Bush Turnpike
Also see: Driver's view of the full 190 corridor, August 19, 2001. | 190/161 construction views
Highway 190/President George Bush Turnpike (190/GBT) is the east-west freeway across the northern Dallas suburbs. It has been on Dallas planning maps since the 1950's and designated a freeway since 1964, but after nearly being cancelled in the 1980's, it came back to life in the early 1990's when construction finally began. This much-needed freeway will be a tollway due to insufficient TxDOT funding for freeways. Nevertheless, it is a top-quality facility, and the north Dallas suburbs are happy to get it any way they can.
On July 31, 2001, the section of the 190/GBT from IH-35E to Marsh opened. This completed the north section of 190/GBT, providing a continous link from IH-35E to Texas 78 in Garland. Construction on the $418 million GBT-Superconnector between IH-35E and 161 at IH-635 should be underway by early 2002, for a 2004 completion. The eastern segment from Texas 78 to IH-30 is scheduled to begin construction in the summer of 2004.
190/GBT is built on a right-of-way width of the corridor is minimum of 400 feet, so there is space for future expansion. Most of the bridges have been built with extra width to facilitate expansion.
190 History and Timeline
| 1950's | Loop 9 is put on city planning maps as a major arterial. |
|---|---|
| 1964 | Loop 9 is elevated to a full freeway in planning documents. |
| Early 1970's | The north section of Loop 9, corresponding to the 190 route, is nearly constructed. |
| 1977 | The freeway alignment is approved and now designated as state highway 190 |
| 1980 | 190 is near death as the TxDOT budget crunch hits and a lawsuit targets the freeway. |
| 1989 | Litigation is settled, in favor of building the freeway. |
| Early 1990's | Feeder roads are constructed from US 75 eastward to state highway 78 |
| Mid 1990's | Feeder roads are constructed from US 75 westward to Coit road (about 3 miles.) |
| 1995 | It is decided to build the facility as a toll road. |
| 1995 | The four-level stack at the Dallas North Tollway is completed. It will stand idle for 4 years. |
| 1997 | The four-level stack at US 75 is completed. |
| 1999 | The first section of tollway opens between US 75 and the Dallas North Tollway |
| 2000 | The east section of the tollway between US 75 and SH78 opens |
| 2001 | On July 31, 2001, the Tollway was completed from IH-35E to Texas 78 in Garland. |
| 2001 | The five-level stack at I-35E will open |
| 2004 | The "super connector" to 161 at I-635 will open. Construction should be underway by early 2002. |
| 2004 | Construction is scheduled to begin on the eastern segment from Texas 78 to IH-30. |
↗ Enlarge