Southern Loop 9 in 2001: Cities Pooled Money to Study a Route

An $823,000 planning effort could help protect a southern freeway corridor. Local leaders hoped to advance construction, while questions about toll financing and development remained.

THE HISTORICAL CONTEXT Reporting dated
Elevated SH 190 ramps under construction span I-35E, with traffic at left and earthmoving equipment beside the freeway.↗ Enlarge

Collection: TexasFreeway archive

Construction in the north; study money in the south.

SH 190 and I-35E stack looking north12-May-2001

The May 12, 2001 view looks north along I-35E at the SH 190 stack under construction. Its elevated ramps show the northern corridor taking shape while officials were still seeking studies for the proposed southern arc. This photograph does not show southern Loop 9 construction.

Original image caption

(high resolution 162k) Looking north along IH-35E at the 190/IH35E stack.

Explore the May 2001 construction photographs →

TexasFreeway commentary · A look back at the decisions, tradeoffs and people behind the road. Newspaper excerpts are credited beside each quotation.

01 / The study money

Southern cities were buying another round of Loop 9 planning

The figures in Donna Logan Wisdom’s July 20, 2001 report were modest beside the cost of a freeway: DeSoto had committed $17,200, Cedar Hill $14,600 and Lancaster $11,800. Those contributions were intended to help pay for studies. For communities wanting the southern Loop 9 corridor sooner, the next useful step still involved reports and a route on a map.

A task force was working to secure $823,000 for a major investment study and a draft environmental impact statement. The yearlong effort was expected to begin in September, followed by local, state and federal review. These were prerequisites for pursuing funding and protecting right of way; the money being sought was for planning, with construction funding still ahead.

Dallas County project manager Don Cranford had been involved for about twenty years. Studies begun in 1995 had been on hold, and the new work would update that information. For local leaders, reviving the study meant returning to an unfinished project rather than starting with a newly invented route.

The North Central Texas Council of Governments would provide federal money for half the study cost. Dallas County would supply a quarter, and communities along the proposed route were asked to contribute. Ellis County and Midlothian were among those that had agreed. Splitting a comparatively small planning bill required cooperation across the same boundaries a future road would cross.

02 / Reserve the land

Loop 9 needed a wide corridor before land became harder to obtain

Grady Smithey, a Duncanville council member who served on the regional transportation committee, gave a practical reason to act early:

“We have to identify a corridor and reserve right of way before it becomes so prohibitively expensive,”

Grady Smithey, quoted by Donna Logan Wisdom, The Dallas Morning News, July 20, 2001

The proposal was for an eight-lane freeway with service roads, built in phases within a 400-foot-wide path. The 1997 estimate was $674.2 million for land acquisition and construction along 40 miles, from I-20 in Mesquite to SH 360 in Mansfield. A route of that width had to fit among the places officials expected to grow.

Preserving right of way kept a future transportation option in view while development decisions were being made. It also left an important question open: when would funding turn the reserved corridor into a road? The regional plan had reduced the southern section to right-of-way preservation only.

The historic freeway-plan chronology gives this effort a longer setting. Its Mobility 2025 section preserves the planning horizon that southern officials were trying to move beyond in 2001.

03 / A different road

The southern arc could not simply copy the Bush Turnpike

The proposed southern section belonged to the same larger loop as the Bush Turnpike and SH 161. The northern projects supplied a visible example of a road influencing growth. Our May 2001 construction photograph shows elevated connections taking shape at SH 190 and I-35E; it shows the northern project, rather than work on the proposed southern route.

The financing prospects differed, too. Dallas County project manager Don Cranford said previous studies had found the southern road a poor candidate for toll financing. The northern turnpike’s progress therefore did not provide a ready-made way to pay for these 40 miles.

Cranford said the regular plan did not call for construction before 2025. Lancaster Mayor Pro Tem James O’Neal sounded more hopeful, suggesting a project once 25 to 30 years away might be ten years away and that service roads would come first. Those were competing expectations about timing, not an announced construction schedule.

04 / Growth and doubt

Lancaster’s development hopes came with a local warning

Wisdom reported substantial population growth during the preceding decade in Cedar Hill, DeSoto and Lancaster. Officials wanted additional travel routes, and some saw future service roads as an opportunity for businesses. The March Loop 9 development story had already described how the northern turnpike could influence airport land and even commuters’ housing choices.

Lancaster council member Vic Buchanon supported the study for regional cooperation while questioning the promise of development. He pointed to the long wait for activity along I-20. That was a pointed local challenge to using the northern turnpike as a forecast for the south: nearby freeway access had not produced the quick result he wanted.

Both positions could support paying for the study. One saw a road as an opportunity to guide growth; the other wanted to avoid promising an economic boom before it happened. In July 2001, the cities were still assembling money to examine a route whose funding, phases and opening dates remained ahead of them.

Photograph viewer

Original image ↗Next collection →