SH 130 in 2002: A Preferred Builder, With an Agreement Still Ahead

TxDOT selected Lone Star Infrastructure for contract discussions. Its official announcement explains how a single agreement could overlap design, construction and land purchases along the proposed bypass.

THE HISTORICAL CONTEXT Archived in April 2002 archive entry; release undated
Preliminary 1999 TxDOT map of proposed SH 130 east of I-35, running from Georgetown past Austin toward Seguin↗ Enlarge

Map: Texas Department of Transportation · © 1999 TxDOT, as printed on the source image.

One proposed corridor. Several stages of work.

Proposed SH 130 route map1999 map

This preliminary 1999 TxDOT map places the proposed SH 130 corridor east of I-35, from Georgetown toward Seguin. It predates the 2002 proposal review and is marked subject to change; it shows the corridor’s scope rather than a completed highway.

Austin freeway planning maps →

TexasFreeway explanation · New context appears first. The complete official TxDOT release is separately labeled below and retains its original wording.

01 / New TexasFreeway explanation

One team would take on several jobs

The name of the winning group was only part of the news. TxDOT wanted SH 130 to become Texas’s first state-highway project under an Exclusive Development Agreement: one consortium would design, build and maintain the road. The attraction was the ability to overlap work that the department traditionally handled in separate steps.

A highway usually moves through design, land acquisition and construction before drivers see the benefit. The release described a different sequence: construction could start on one section while design and land purchases continued elsewhere. That could save time across a long corridor, although it did not remove any of those jobs. Someone still had to draw the plans, buy the land and pour the concrete.

TxDOT’s two-month review compared three proposals. Lone Star Infrastructure ranked first, Four Rivers Developers second, and Texas Corridor Constructors was the third bidder. The department said its evaluation considered innovation, construction cost, scheduling and maintenance costs over the coming 15 to 30 years. A “best value” choice therefore meant more than finding the smallest construction price. The release does not provide the scores or prices needed to compare the bids ourselves.

02 / New TexasFreeway explanation

The announcement was a beginning, not the construction contract

The next steps were stated plainly. TxDOT and the preferred consortium would enter discussions immediately, with officials hoping to finish an agreement within two months. The Texas Transportation Commission still had to approve the selection and award it. The release tied the start of detailed design and right-of-way acquisition to approval of that agreement.

The proposed road stretched roughly 90 miles, from I-35 north of Georgetown to I-10 near Seguin. Officials expected the agreement to cover that whole distance, but initial work to concentrate on the northern portion ending south of Austin-Bergstrom International Airport. Those are two different scopes: a corridor-wide agreement and a more limited first construction effort. The earlier eastern-route decision explains how that corridor had been chosen.

The preliminary 1999 map beside the opening shows SH 130 running east of I-35 past Austin and toward Seguin. It was marked subject to change, and it predates this contracting announcement. For a road of that length, the ability to build one section while finishing work on another was the practical point of the proposed agreement. Environmental approval and right-of-way funding had already been separate hurdles; selecting a builder brought another decision closer without settling the others.

03 / Official TxDOT news release · undated

Review of State Highway 130 proposals completed

The following is the complete official release, with its original wording retained. The archive filename is dated April 8, 2002; no date is printed in the release itself.

Official TxDOT news release

(Austin) - Long Star Infrastructure - a consortium of engineering and construction firms with world-wide experience - offers the best long term value of three groups proposing to build State Highway 130, according to an evaluation just completed by the Texas Department of Transportation (TxDOT). Contract discussions will begin immediately between TxDOT's Turnpike Authority Division and Lone Star Infrastructure on an agreement under which the consortium would design, construct, and maintain SH 130.

This will be the first Exclusive Development Agreement for a state highway project in Texas. Such agreements will accelerate needed highway improvements by allowing the state to hire one consortium to do all the work on a project - much of it simultaneously - rather than the traditional development process in which the state divides the funding, design, construction and maintenance into separate steps. "This is good news for Central Texas motorists," said state senator Gonzalo Barrientos. "Upon its completion, SH 130 should alleviate some of the congestion currently making Interstate 35 as it runs through Austin the most dangerous stretch of that highway in the country. Getting the road built will be very much a team effort, as it has been just to get to this point. I'm confident that TxDOT, the Texas Transportation Commission, CAMPO, and the cities and counties involved will continue to work together as this project develops." Turnpike officials hope to have a final agreement within the next two months.

"We are moving full speed ahead," said Mike Behrens, TxDOT executive director. "Because of its size and scope, SH 130 is uniquely qualified for an exclusive development agreement and completing the proposal evaluations is another major accomplishment getting us closer to making the highway a reality." As soon as the exclusive development agreement is approved, right of way acquisition and detailed design work can begin. The Texas Transportation Commission must approve the selection of Lone Star Infrastructure as the best value proposer and award the agreement. With an exclusive development agreement, construction can begin while design work and right of way acquisition continues on other parts of the corridor. Traditionally, design work is completed and right of way acquired before TxDOT hires a contractor to build a project.

The decision to enter contract discussions with Lone Star Infrastructure comes after an extensive two-month review of proposals from three groups on SH 130 - a proposed toll road that will relieve congestion on I-35 and other major roadways in the Austin/San Antonio corridor. In evaluating the proposals, TxDOT looked for innovative thinking in addition to considering construction cost, scheduling, and long term maintenance cost. TxDOT officials determined that Lone Star Infrastructure submitted the proposal that offers the best value to taxpayers and motorists for the next 15 to 30 years. The other consortiums submitting proposals were Four Rivers Developers, ranking second after the evaluation of the proposals, and Texas Corridor Constructors. When completed, SH 130 will stretch some 90 miles from I-35 north of Georgetown to I-10 near Seguin. The exclusive development agreement would be for the entire distance, but TxDOT officials expect initial work to focus on the northern section from Georgetown to south of Austin-Bergstrom International Airport.