01 / MOPAC SCHEMATICS
Downtown to Windsor
↗ Enlarge2001 preliminary design
Downtown interchange
Changes to the downtown interchange at 1st and 5th Streets will be minimal. Only HOV connections will be added.
↗ Enlarge2001 preliminary design
Enfield intersection
This view shows the new configuration and HOV connections.
↗ Enlarge2001 preliminary design
Enfield-Windsor
In this section, residences on both sides of the freeway would be displaced. The design also includes interwoven entrance/exit ramps south of Windsor.
↗ Enlarge2001 preliminary design
Windsor intersection
The cloverleaf connections would be removed.
↗ Enlarge2001 preliminary design
Windsor-Westover
In this section, most displacements would occur on the west side of the existing freeway.
02 / MOPAC SCHEMATICS
Westover to Camp Mabry
↗ Enlarge2001 preliminary design
Westover
The Westover interchange would be permanently closed.
↗ Enlarge2001 preliminary design
Westover to 35th
Most right-of-way acquisition is on the west (top) side.
↗ Enlarge2001 preliminary design
35th-Camp Mabry
The design shows a major re-configuration of this interchange, including removal of the cloverleafs and a new entrance ramp to northbound Mopac that would require the demolition of a TxDOT building.
↗ Enlarge2001 preliminary design
Camp Mabry
The design shows that many Camp Mabry buildings would be affected, and the jogging trail would need to be re-routed.
↗ Enlarge2001 preliminary design
Mabry-45th
This shows the re-configuration of the 45th street intersection.
03 / MOPAC SCHEMATICS
North MoPac to US 183
↗ Enlarge2001 preliminary design
45th-Hancock
Right-of-way acquisition is along the west side.
↗ Enlarge2001 preliminary design
2222 wide view
The design shows a new entrance ramp to northbound Mopac, and shows HOV connector ramps to Balcones Road.
↗ Enlarge2001 preliminary design
Steck
There is sufficient right-of-way in this section to accommodate the extra lanes.
↗ Enlarge2001 preliminary design
183 Stack
The 183 frontage roads are shown as being continued through the intersection. A new HOV connector ramp is added. Businesses are displaced south of 183 to make room for the extra lanes on Loop 1.
04 / ORIGINAL ARCHIVE ACCOUNT
Loop 1 (Mopac Blvd) 2001 Preliminary Schematic, for Historical Reference
Last updated
Also see: Mopac Photo Gallery | Mopac Construction Photos
The official project web site: http://www.mopac183.com/
This is the design that stirred up the protest army at the 9-April-2001 public hearing at the Austin regional planning council meeting. The opposition was about 800 people strong and even had former Texas governor Ann Richards on their side. The study for improvements to Loop 1 was suspended in February 2002 and remains suspended as of this writing in December 2003. Austin now has a regional mobility authority, and if anything happens in the future for this project it will likely be through the mobility authority.
These schematics represent the leading design candidate as of 2001. If and when the Loop 1 study is resurrected, the plan could be similar to this design, or it could be different.
This design was an option under consideration in 2001. As of December 2003, planning for future improvements to Loop 1 is on hold.