Follow the proposed changes from downtown to US 183. Fourteen schematic views show the ramps, interchanges and neighboring properties considered in the 2001 design.

Explore the schematics ↓ Read the original account

These are historical proposals. The original descriptions below reflect the 2001 design and the page’s December 2003 update.

01 / MOPAC SCHEMATICS

Downtown to Windsor

2001 preliminary MoPac schematic: Downtown interchange↗ Enlarge

2001 preliminary design

Downtown interchange

Changes to the downtown interchange at 1st and 5th Streets will be minimal. Only HOV connections will be added.

2001 preliminary MoPac schematic: Enfield intersection↗ Enlarge

2001 preliminary design

Enfield intersection

This view shows the new configuration and HOV connections.

2001 preliminary MoPac schematic: Enfield-Windsor↗ Enlarge

2001 preliminary design

Enfield-Windsor

In this section, residences on both sides of the freeway would be displaced. The design also includes interwoven entrance/exit ramps south of Windsor.

2001 preliminary MoPac schematic: Windsor intersection↗ Enlarge

2001 preliminary design

Windsor intersection

The cloverleaf connections would be removed.

2001 preliminary MoPac schematic: Windsor-Westover↗ Enlarge

2001 preliminary design

Windsor-Westover

In this section, most displacements would occur on the west side of the existing freeway.

All chapters Back to top ↑

02 / MOPAC SCHEMATICS

Westover to Camp Mabry

2001 preliminary MoPac schematic: Westover↗ Enlarge

2001 preliminary design

Westover

The Westover interchange would be permanently closed.

2001 preliminary MoPac schematic: Westover to 35th↗ Enlarge

2001 preliminary design

Westover to 35th

Most right-of-way acquisition is on the west (top) side.

2001 preliminary MoPac schematic: 35th-Camp Mabry↗ Enlarge

2001 preliminary design

35th-Camp Mabry

The design shows a major re-configuration of this interchange, including removal of the cloverleafs and a new entrance ramp to northbound Mopac that would require the demolition of a TxDOT building.

2001 preliminary MoPac schematic: Camp Mabry↗ Enlarge

2001 preliminary design

Camp Mabry

The design shows that many Camp Mabry buildings would be affected, and the jogging trail would need to be re-routed.

2001 preliminary MoPac schematic: Mabry-45th↗ Enlarge

2001 preliminary design

Mabry-45th

This shows the re-configuration of the 45th street intersection.

All chapters Back to top ↑

03 / MOPAC SCHEMATICS

North MoPac to US 183

2001 preliminary MoPac schematic: 45th-Hancock↗ Enlarge

2001 preliminary design

45th-Hancock

Right-of-way acquisition is along the west side.

2001 preliminary MoPac schematic: 2222 wide view↗ Enlarge

2001 preliminary design

2222 wide view

The design shows a new entrance ramp to northbound Mopac, and shows HOV connector ramps to Balcones Road.

2001 preliminary MoPac schematic: Steck↗ Enlarge

2001 preliminary design

Steck

There is sufficient right-of-way in this section to accommodate the extra lanes.

2001 preliminary MoPac schematic: 183 Stack↗ Enlarge

2001 preliminary design

183 Stack

The 183 frontage roads are shown as being continued through the intersection. A new HOV connector ramp is added. Businesses are displaced south of 183 to make room for the extra lanes on Loop 1.

All chapters Back to top ↑

04 / ORIGINAL ARCHIVE ACCOUNT

Loop 1 (Mopac Blvd) 2001 Preliminary Schematic, for Historical Reference

Last updated

Also see: Mopac Photo Gallery | Mopac Construction Photos

The official project web site: http://www.mopac183.com/

This is the design that stirred up the protest army at the 9-April-2001 public hearing at the Austin regional planning council meeting. The opposition was about 800 people strong and even had former Texas governor Ann Richards on their side. The study for improvements to Loop 1 was suspended in February 2002 and remains suspended as of this writing in December 2003. Austin now has a regional mobility authority, and if anything happens in the future for this project it will likely be through the mobility authority.

These schematics represent the leading design candidate as of 2001. If and when the Loop 1 study is resurrected, the plan could be similar to this design, or it could be different.

This design was an option under consideration in 2001. As of December 2003, planning for future improvements to Loop 1 is on hold.

All chapters Back to top ↑

Photograph viewer

Original image ↗Next collection →