The federal loan could speed SH 130, SH 45 North, 183A and the MoPac extension. Environmental approval, bonds, state money and land still had to follow.

THE HISTORICAL CONTEXT Reporting dated
Traffic at the signals at US 183 and RM 620 in August 2001.↗ Enlarge

Collection: TexasFreeway archive

US 183 at RM 620 · August 2001

US 183 and RM 620 intersectionAugust 25, 2001

This photograph was taken nine months after the loan announcement. Traffic still meets at signals at US 183 and RM 620—the area where the proposed 183A bypass would begin. It gives the funding story a place on the ground.

Original image caption

A. This is the intersection of 183 and 620, August 25, 2001. Construction to upgrade 183 to a freeway was in progress. 620, which goes from top to bottom, will be replaced by the SH-45 tollway. In the long run, a 5-level stack is planned for this intersection.

Explore US 183 at RM 620 →

TexasFreeway commentary · A reading of the contemporary reporting. Selected attributed quotations retain the original words; the surrounding analysis is new.

01 / Borrowing against future tolls

A federal loan for roads still on paper

In November 2000, Central Texas had a toll-road program larger than its ready cash. Janet Jacobs reported that an $800 million federal loan could speed four Austin-area projects: SH 130, SH 45 North, US 183A and the northern MoPac extension. The Texas Turnpike Authority said the loan could move construction ahead by as much as 25 years, with all four roads possibly finished in eight to ten years.

“The $800 million is the largest loan ever approved from the pool of money created by the Transportation Infrastructure Finance and Innovation Act of 1998.”

Janet Jacobs, Austin American-Statesman, November 22, 2000

The loan was approved subject to environmental clearance. Turnpike Authority chairman Pete Winstead’s construction timetable also depended on assembling the rest of the financing. Repayment terms would depend on when the state drew down the money.

The repayment plan explains why tolling was at the center of the story. The federal government would lend money early, then future drivers would pay it back through toll collections. Officials were trying to turn later toll revenue into earlier construction money.

“The federal government allows some leeway in the first part of the loan process, but the money eventually would be paid back by the tolls collected from drivers, Winstead said.”

Janet Jacobs, Austin American-Statesman, November 22, 2000

The August 2001 photograph at US 183 and RM 620 shows the signalized intersection near the planned start of 183A. That bypass was intended to take through traffic off the existing road through Cedar Park.

02 / The rest of the undertaking

The rest of the money still had to line up

The four projects were moving at different speeds. A frontage road for SH 45 between County Road 170 and County Road 172 in Round Rock was scheduled to begin in December 2000. The MoPac extension had a contractor selected for a $13 million project. Environmental approval for the other three projects was expected in early 2001.

Turnpike director Phil Russell said the state had only a third of the money needed for identified transportation projects. He was candid about why that shortage made toll roads attractive:

“With that shortage, we have to look for more creative funding methods. If there wasn't such urgency, we'd probably still be looking at these as free projects.”

Phil Russell, Texas Turnpike Authority director, quoted by Janet Jacobs, November 22, 2000

“Although officials were celebrating Tuesday, the projects still face some hurdles, including the environmental approval. The other $2.2 billion needed for the projects is not yet certain, because $1 billion is contingent on the sale of Turnpike Authority bonds and $700 million is supposed to come from the Texas Department of Transportation.”

Janet Jacobs, Austin American-Statesman, November 22, 2000

Buying the land alone could cost as much as $500 million. County officials worried that the real estate boom would push their costs higher. For the MoPac extension, the commission offered to cover half the land cost—about $34 million—if local governments paid the rest. Even with the federal loan approved, counties still faced substantial commitments close to home.

Photograph viewer