↗ EnlargePlanned I-69 routing in Texas, as shown in the 2001 account.
I-69 Texas corridor mapLufkin and Nacogdoches See the approved location of the I-69 bypass
Houston See the route options that have been determined to be feasible.
I-69 Alliance See the official web site of the I-69 Texas Alliance, which includes a comprehensive project listing.
01 / STATEWIDE OVERVIEW
The planned Texas corridor
The currently planned routing of I-69 in Texas is shown in the image. In northeast Texas, this map shows I-69 going to Shreveport in Louisiana, and a separate route connecting to Texarkana. The extension of I-49 will also pass through Texarkana. I-69 follows US 59 into Houston.
I-69 will most likely bypass Houston using the northern and western segments of the Grand Parkway. Southwest of Houston, I-69 follows the route of US 59 again.
In South Texas, this map shows three branches of I-69. As of August 2000, all three of these routes are in the official plan. The branch to Laredo will follow US 59. Both US 77 (the eastern route) and US 281 will be upgraded to interstate status and connect to the Rio Grande Valley (far south Texas). I'm skeptical that both these routes are needed. We'll see if both routes survive to the final plan.
There is practically no opposition to I-69 in Texas. In fact, East Texas and South Texas are desperate for this interstate. The only thing holding it back is lack of money.
| Existing Facility | I-69 will generally follow the route of US 59. In south Texas, it will follow US 77 and US281 on two parallel routes to the Rio Grande Valley. These existing routes are mostly four-lane divided highways. |
|---|---|
| Proposed Facility | A fully controlled-access freeway facility. The route will be built on new location where necessary, such as the Lufkin-Nacogdoches bypass and the Houston bypass. |
| Length | Approximately 1000 miles of roadway in Texas. The entire I-69 corridor is 1600 miles long. |
| Cost | A July 2000 TxDOT request for consultant services lists the Texas construction cost at $5.5 billion. I had previously seen this cost figure for the entire I-69 corridor. However, the extra mileage in Texas and the Houston bypass has surely increased the cost. |
| Status | Comprehensive environmental studies are underway. A major contract for study of the corridor will be awarded in the third quarter of 2000. |
| Construction | Most likely to occur in the 2005-2015 time frame. |
02 / SOUTH TEXAS
How Will the Three Branches in South Texas be Numbered?
At this time, no decision has been made.
According to the federal legislation, the link to McAllen via 281 is designated as "Central", and the link to Harlingen via 77 is designated as "East". The northernmost of the three branches, which terminates in Laredo, does not have a special designation. Presumably, it is simply "I-69". This suggests a naming convention of I-69 for the branch to Laredo, I-69C for the central branch, and I-69E for the eastern branch. However, federal policy seems to rule out using letters for future interstate designations.
So, it will probably be years before we know how the 3 branches will be designated.
03 / RECENT EVENTS
Recent Events (as of January 2001)
On December 13, 2000, the Houston Chronicle published an article in which one of the members of the three-person Texas Transportation Commission speculated that I-69 will follow the route of the Grand Parkway around Houston. A final decision will probably occur around 2004. See the article, "Highway official envisions merger of I-69, parkway".
In July 2000, TxDOT advertised for consultant services for a comprehensive environmental and routing study of the entire corridor in Texas. From the TxDOT request for services:
"The approximately 1,000 miles of the Texas IH 69 project is part of a national corridor that continues up to Indiana and Michigan. The approximately 1,600 mile IH 69 corridor is recognized as one of the largest public infrastructure projects currently under development in the nation. The department is interested in a project manager and team that has demonstrated capabilities to successfully manage route location studies, environmental documents and schematics for similar projects that are multi-state or at least 100 miles in length."
On June 9, 2000, the US Department of Transportation awarded Texas $13,065,000 for the Environmental Study for Corridor 18 from northeast Texas to lower Rio Grande Valley. This corridor will probably be under study until 2007.
In the second quarter of 2000, the final routing for the I-69 bypass of Lufkin and Nacogdoches was announced.
In the first quarter of 2000, the feasible routes around and through Houston were identified.
04 / LUFKIN AND NACOGDOCHES
Lufkin and Nacogdoches
Most of this information was extracted from the US59 project web site.
The study of Lufkin and Nacogdoches started in 1997 and was recently concluded with a route recommendation. I-69 will follow a new location route around Lufkin and Nacogdoches, following the "tight S" option.
↗ EnlargeProposed I-69 bypass route around Lufkin and Nacogdoches
↗ EnlargeProposed I-69 bypass alignment around Lufkin and Nacogdoches
| Existing Facility | US 59. This is a highway with traffic lights and some grade separations. |
|---|---|
| Proposed Facility | A full bypass freeway. The freeway will be on a new location for nearly the entire route. |
| Length | Approximately 40 miles |
| Cost | $420 million for construction, $18.2 million for right-of-way. |
| Status | Final alignment determined in May 2000 |
| Right of way acquisition | To begin in 2001 |
| Construction | Most likely to occur in the 2007-2010 time frame. |
↗ EnlargeLufkin–Nacogdoches proposed route map
High resolution (74k) Medium resolution (88k)
05 / HOUSTON
Houston
For more information see the I-69 Study web site.
In early 2000, a feasibility study for the routing of I-69 in the Houston area was concluded. The study identified several "feasible" routes, including some riduculus routes around the south and east sides of Houston. (See map)
Based on news reports, I think there is a very high probability that the route using the northern and western Grand Parkway (SH 99) will be selected. The map also shows a new spur to the existing section of the Grand Parkway between US59 and I-10 on the southwest side. (The existing SH99 is the eastern alternative shown and is less direct than the western alternative.) Estimated cost for this route is $1.96 billion. Ouch!!!
The Grand Parkway section between US 59 south and I-10 West opened in 1994. Most of it is not a freeway, but can be easily upgraded to a freeway by adding grade separations at interchanges. The rest of the Grand Parkway is currently in various stages of study. See the Grand Parkway web site for more information.
Download the final report. (Adobe Acrobat)
↗ EnlargeProposed I-69 corridor alternatives in the Houston region
High resolution (217k) Medium resolution (87k)