Connector construction at Hardy Toll Road / Beltway 8
Last updated 21-December-2001
| Project
| Add 1 direct connector, eastbound Beltway 8 to northbound Hardy Toll Road
|
| Cost
| $12.4 million
|
| Begin
| Q1 2000
|
This will greatly improve the accessibility of the Hardy Toll Road from Beltway 8.
|
|
This is a map view of the new connector from EB BW8 to the NB Hardy Toll road. This will be the first direct connector at this interchange. Connections presently must be made via the feeders. At .905 miles (1.46 km) long, this is a very long ramp.
December 20, 2001
Looking east along the eastbound Beltway 8 feeder. On December 20, 2001, a long line of columns were in place. 20-December-2001.
(high resolution 179k) Looking at the construction across Beltway 8. 20-December-2001.
This view looks north along the Hardy Toll Road. 20-December-2001.
May 2001
(high resolution 94k) Looking north along the Hardy Toll Road. On May 20, 2001, the piers along the Hardy Toll Road were in place. 20-May-2001.
|