Stack construction at IH-45 / Beltway 8 North

Last updated 21-December-2001

Project Build 4 direct connectors to complete the 5-level stack.
Cost $36.4 million
Begin Q1 2000

Two direct connectors were constructed in the late 1960's for the opening of Houston Intercontinental Airport in 1969. Construction completed in 1998 replaced one of those two connectors, and added 2 new connectors for a total of 4 complete connectors. This project will build the 4 remaining direct connectors.

Construction location: IH45/BW8

December 20, 2001
IH-45/BW8 west
(high resolution 194k) Looking north along the soutbound IH-45 feeder road. Photo taken 20-December-2001.

IH-45/BW8 west
(high resolution 207k) Driver's view going eastbound on the BW8 feeder. The ramp from eastbound BW8 to southbound IH-45 (on the right side of the photo) is nearly complete. Photo taken 20-December-2001.

IH-45/BW8 west
Looking west along the westbound BW8 feeder. Photo taken 20-December-2001.

May 2001
IH-45/BW8 west
(high resolution 91k) Looking north along the IH-45 feeder road. Photo taken 20-May-2001.

October 2000

Construction of direct connector ramps at the BW8/IH-45 interchange, October 2000. This view looks east, showing piers for the connector from eastbound BW8 to southbound IH-45.


Construction of direct connector ramps at the BW8/IH-45 interchange, October 2000. This view looks east, showing piers for the connector from northbound IH-45 to westbound BW8.

 
Austin
| Corpus Christi | Dallas/Fort Worth | El Paso | Houston | San Antonio
Statewide | Other Resources | about TexasFreeway.com | Contact Info | Home | Site Index
 
TexasFreeway.com is not associated with TxDOT or any other government agency.
All information is unofficial and "AS IS" with no guarantees for accuracy. All schematics are preliminary except as noted.
 
© 2007-2008 TexasFreeway.com