Created and last updated June 10, 2001
Go to 114 main page
In May 2001, there was $40.4 million work in progress, about 70% complete.
An additional $36.5 million in contracts will be awarded in summer 2001 to complete this section of freeway.
Photos taken May 14, 2001.
(high resolution 151k) Looking west at the current end of the freeway at Southlake Boulevard.
Construction can be seen just on the other side of the overpass.
(high resolution 293k) Looking west from the Southlake overpass.
(high resolution 191k) Looking west from west of Southlake.
(high resolution 141k) Looking back eastward towards the Southlake overpass.
(high resolution 159k) The new overpass at Kimball road.
(high resolution 159k) Looking east at the Dove road overpass, which is about 2-3 miles west of Kimball.
(high resolution 138k) Between Dove Road and Kimball, construction has not yet begun. About $36.5 million in contracts will be
awarded in summer 2001. The right-of-way will be substantially widened to about 400 feet (122m). Displacements will be minimal since
most of the land in the corridor is vacant.