Major Construction in Progress, November 2001
Location Cost $
(millions)
Start Finish Description
I-35 - 290 south/SH71/Ben White Blvd 87.8 10/99 2003 Build 71 main lanes, rebuild IH-35, build 4 direct connectors
183 north 50.5 10/99 Q4/01 Upgrade to 6 lane freeway with 6 lane feeders
I35, north of Georgtown 34.2 6/00 2002 Add one lane in each direction for 6 lane freeway

Completed Projects
Towne Lake Pedestrian Bridge Completed in June 2001
IH-35 north at 290 Four direct connectors. The $28.2 million project opened 8-November-2001.
SH 45 north (Round Rock, TX) Frontage roads, completed 2002. Cost: $13.1 million

 
Austin | Corpus Christi | Dallas/Fort Worth | El Paso | Houston | San Antonio
Statewide | Other Resources | about TexasFreeway.com | Contact Info | Home | Site Index
TexasFreeway.com is not associated with TxDOT or any other government agency.
All information is unofficial and "AS IS" with no guarantees for accuracy. All schematics are preliminary except as noted.
© 2005 TexasFreeway.com